Excavation Calculator
Calculate earthwork volume, backfill quantity, disposal load, number of truck trips, and excavation cost for foundations, trenches, basements, and pools.
Excavation Volume Calculator
Foundation Pit · Trench · Basement · Sloped Cutting
Excavation Results
CalculatedHow Excavation Volume is Calculated
Bank vs Loose vs Compacted Volume
Soil Swell & Load Factors Reference
| Soil Type | Swell Factor | Load Factor | Angle of Repose |
|---|---|---|---|
| Loose Sand | 10–12% | 0.89–0.91 | 30°–35° |
| Sandy Loam | 15–18% | 0.85–0.87 | 25°–35° |
| Clay Loam | 20–25% | 0.80–0.83 | 15°–25° |
| Hard Clay | 28–35% | 0.74–0.78 | 10°–20° |
| Soft Rock | 35–40% | 0.71–0.74 | 45°–55° |
| Hard Rock | 40–60% | 0.63–0.71 | 60°–80° |
Worked Example: Strip Footing Trench for a House
A house with 30 m of wall footing, dug as a trench 0.9 m wide and 1.2 m deep in loam or clay. The calculator's defaults are used: 20% swell, 40% of the dug volume going back as backfill, and 5 m³ dumper trucks.
| Step | Working | Result |
|---|---|---|
| Bank (in-situ) volume | 30 × 0.9 × 1.2 | 32.40 m³ |
| Loose volume after digging | 32.40 × 1.20 | 38.88 m³ |
| Kept for backfill | 32.40 × 0.40 | 12.96 m³ |
| To carry away | 38.88 − 12.96 | 25.92 m³ |
| Truck trips | 25.92 ÷ 5, rounded up | 6 trips |
Why Side Slopes Matter
A basement pit with a 6 × 4 m base, 2 m deep, holds 48 m³ if the sides could stand vertical. With the calculator's default side slope of 1:2 (half a metre out for every metre down), the top opens to 8 × 6 m and the prismoidal formula gives:
That is almost 50% more soil to dig and move than the vertical-sided estimate, and the gap grows quickly with depth and with flatter slopes. If the site is too tight for slopes, the alternative is shoring, which has its own cost.
Practical Tips
Working space. Footings and basement walls need room for formwork, waterproofing and workers. The rectangular pit option adds a working space on every side, 0.5 m by default; leaving it out under-estimates both the dig and the backfill.
Backfill is not the whole loose volume. Soil returned around a footing is compacted in layers and settles back towards its in-situ volume. Plan the quantity on the bank volume, as the calculator does, and expect to bring in fill if the dug soil is unsuitable.
Groundwater and soft spots. Wet or soft ground changes both the slope you can use and the time the job takes. A short trial pit before pricing tells you far more than any table.
Spoil heaps. Keep excavated soil well back from the edge of the trench. The extra load near the edge is a frequent cause of collapses, and the heap also takes up the space you need for the work.