Earthworks & Sitework

Excavation Calculator

Calculate earthwork volume, backfill quantity, disposal load, number of truck trips, and excavation cost for foundations, trenches, basements, and pools.

Excavation Volume Calculator

Foundation Pit · Trench · Basement · Sloped Cutting

Pit length at bottom
Pit width at bottom
Excavation depth
Extra clearance around foundation
Volume increases after excavation
% of volume returned as backfill
Dumper truck volume
Local rate per cubic meter

Excavation Results

Calculated
—
m³
Net Volume
—
m³
Bulk Volume
—
m³
Backfill Volume
—
m³
Disposal Volume
—
trips
Truck Trips
—
PKR
Est. Cost
—

How Excavation Volume is Calculated

Bank vs Loose vs Compacted Volume

Bank Volume = L × W × D (in-situ, before excavation) Bulk/Loose Vol = Bank Vol × (1 + Swell Factor%) [for trucks] Backfill Vol = Bank Vol × (Backfill%) [returned to pit] Disposal Vol = Bulk Vol − Backfill Vol [remove from site] Truck Trips = Disposal Vol ÷ Truck Capacity Sloped Pit Vol = D/6 × (A_bottom + A_top + 4×A_middle) [Prismoidal] Circular Pit = π × r² × D
Always add 10–20% wastage to excavation volumes for site irregularities, over-excavation, and measurement tolerances.
Excavation deeper than 1.5m requires shoring, timbering, or sloped sides per Pakistan safety regulations. Always consult a geotechnical engineer for deep excavations.

Soil Swell & Load Factors Reference

Soil TypeSwell FactorLoad FactorAngle of Repose
Loose Sand10–12%0.89–0.9130°–35°
Sandy Loam15–18%0.85–0.8725°–35°
Clay Loam20–25%0.80–0.8315°–25°
Hard Clay28–35%0.74–0.7810°–20°
Soft Rock35–40%0.71–0.7445°–55°
Hard Rock40–60%0.63–0.7160°–80°

Worked Example: Strip Footing Trench for a House

A house with 30 m of wall footing, dug as a trench 0.9 m wide and 1.2 m deep in loam or clay. The calculator's defaults are used: 20% swell, 40% of the dug volume going back as backfill, and 5 m³ dumper trucks.

StepWorkingResult
Bank (in-situ) volume30 × 0.9 × 1.232.40 m³
Loose volume after digging32.40 × 1.2038.88 m³
Kept for backfill32.40 × 0.4012.96 m³
To carry away38.88 − 12.9625.92 m³
Truck trips25.92 ÷ 5, rounded up6 trips
Contractors are normally paid on the bank volume, measured from the drawings or from levels before and after digging. Trucks, though, carry the loose volume. That is why the trip count is based on the swollen figure, not the measured one.

Why Side Slopes Matter

A basement pit with a 6 × 4 m base, 2 m deep, holds 48 m³ if the sides could stand vertical. With the calculator's default side slope of 1:2 (half a metre out for every metre down), the top opens to 8 × 6 m and the prismoidal formula gives:

A bottom = 6 × 4 = 24 m² A top = 8 × 6 = 48 m² A middle = 7 × 5 = 35 m² Volume = 2 ÷ 6 × (24 + 48 + 4 × 35) = 70.67 m³

That is almost 50% more soil to dig and move than the vertical-sided estimate, and the gap grows quickly with depth and with flatter slopes. If the site is too tight for slopes, the alternative is shoring, which has its own cost.

Practical Tips

Working space. Footings and basement walls need room for formwork, waterproofing and workers. The rectangular pit option adds a working space on every side, 0.5 m by default; leaving it out under-estimates both the dig and the backfill.

Backfill is not the whole loose volume. Soil returned around a footing is compacted in layers and settles back towards its in-situ volume. Plan the quantity on the bank volume, as the calculator does, and expect to bring in fill if the dug soil is unsuitable.

Groundwater and soft spots. Wet or soft ground changes both the slope you can use and the time the job takes. A short trial pit before pricing tells you far more than any table.

Spoil heaps. Keep excavated soil well back from the edge of the trench. The extra load near the edge is a frequent cause of collapses, and the heap also takes up the space you need for the work.

Frequently Asked Questions

Bank volume (BCM) is the volume of soil in its natural, undisturbed state in the ground. Loose volume (LCM) is the volume after excavation, when soil expands due to air gaps between particles. Clay typically swells 20–30%, so 100 m³ of bank clay becomes 120–130 m³ loose — affecting truck load calculations and disposal costs.
Standard dumper truck sizes in Pakistan: Small (Suzuki): 2–3 m³ · Medium: 5–6 m³ · Large (10-wheeler): 8–12 m³. For BOQ purposes, 5 m³ is the most common standard truck size. Always verify with your contractor as actual capacities vary by vehicle and payload limits.
Approximate excavation rates in Pakistan (2025): Manual excavation (soft soil): PKR 300–500/m³ · Machine excavation (JCB/excavator): PKR 400–700/m³ · Disposal (with truck): PKR 200–400/m³ extra · Hard soil/murram: +30–50% above above rates. Rates vary by city, soil type, and site access.